DATE:  19/08/04 

 
Dear Ken,

Subject:  Practical Completion

Practical completion for Auburn Home Mega Mall was achieved on Saturday 3rd July 2004.  WALTER Construction Group (Auburn Site Team) would like to acknowledge and extend our appreciation to all involved for delivering a successful project to our client.

Should the opportunity arise, we look forward to continuing this successful relationship on future projects.

Once again, your contributin to Auburn Home Mega Mall has been greatly appreciated.

Kind Regards,

Tim McCann
Project Manager


 DATE:  10/02/05

 

 

Ken,

Firstly I would like to say big thank you for the relationship that we have been able to establish between DORMA BWN and Gleco Enterprises.  With the relationship now strong we can go forward with the future.

I have received your Invoice for Dymocks Erina and I must say for the first time in a long time, working the subcontractors I have no problem in paying this Invoice.  Gavin and Doug on this night worked to get the job at hand complete and at no stage of the project did I doubt their ability to complete the said works.

I must say that the way in which they carried themselves in such a professionism was amazing.  They are both a Credit to you, your establishment and themselves.

Thank you once again, I look forward to a long lasting working relationship.

Craig Sargent
NSW Service - Install Manager
DORMA BWN AUTOMATICS


 

 

 

 Attention:      Ken Ewings

Dear Sir,

RE:    PROJECT DEBRIEF NOTE
         OFFICEWORKS CAMPBELLTOWN

Thank you for providing your services at Officeworks, Campbelltown.

Of the twenty eight subcontractors on the project, your firm scored the following marks, evaluated by a panel of people involved in the project including site manager, estimator, project manager and others:

Safety.........................................4/5
Quality of Workmanship................4/5
Performance................................4/5
Standard of Documentation............4/5
Variations.....................................4/5

The average total score for subcontractors on this site was 19.6.  Your  total, at 20, was 0.4 above the average.  You were ranked 17 out of the 28 subcontractors on the site.

Yours sincerely,
Kell & Rigby

James Kell